Construction Powering Ahead – Major Milestones Achieved
INNOVA Rochedale is progressing rapidly, with key construction milestones now complete and the site transforming into Rochedale’s premier business destination.


Site Progress Snapshot:
Underground Services – Complete
- Water, electrical, and drainage fully installed
- Civil works fully completed, including concrete footings now in place and ready for tilt-up panels
Casting Beds – Prepped and Ready
- Concrete panel pours commencing in the coming weeks
Concrete Panel Installation – Starting Soon
- Installation of concrete panels to begin in the coming weeks
- Roofing to follow once concrete panels are in place
INNOVA Rochedale is rapidly advancing towards becoming a leading business and logistics hub in the region.