Skip to main content

Construction continues to progress at INNOVA Shailer Park, with further milestones achieved across the development this October.

• Buildings A & B: Tilt panel lifts underway.
• Building C: Roof works, including gutter installation, complete.
• Building D: Internal subsoil services nearing completion.
• Building D: Internal slab preparation and concrete pouring underway.
• Building D: Mezzanine balustrade installation underway.

Practical Completion remains scheduled for Q1 2027.

Limited warehouse opportunities remain available from 104 m².